Build Resilient Future-Proofed Pipelines

The Series 36 PE tailed gate valve, is everything you would expect from an AVK gate valve, especially when it comes to pipeline resilience.

Built with factory-fitted PE-tails, the AVK gate valves are engineered to deliver resilient pipelines, reduce installation times, improve water security, reduce leak paths and make installation easier for all involved. Additionally, when paired with AVK Smart Water you’ll gain the intelligence you need to build and optimise the networks of tomorrow.

With pressure on the UK Water Industry to build more resilient pipelines and improve efficiencies, the AVK's PE-Tailed Gate Valve helps you create the networks of tomorrow, today.

No Potential Leak Paths

When compared to an equivalent flanged gate valve installation, the factory fitted and sealed PE-tailed pipes on the AVK Series 36 gate valve present no potential leak paths. 

When installed using best-practice electrofusion welding, the AVK Series 36 gate valve creates a fully welded and durable pipeline to stand the test of time. It will deliver a significant reduction in non-revenue water, reinforces network resilience and enhance water security.

AVK's PE tailed gate valves present no potential leak paths. Equivalent flanged gate valves can have two potential leak paths because of their two bolted mechanical joints. These PE tailed gate valves do not require flanges because the valves factory-fitted PE tails are fully welded into the network using electrofusion couplers.

40% Faster to install

When compared to equivalent flanged gate valve installations, the AVK Series 36 requires far fewer components: no nuts, no bolts, no washers, no flanges, no stub flanges, no tape. It’s a far more efficient and quicker installation process.

During independent time trials, an AVK Series 36 installation required 40% less time than an equivalent flanged gate valve. Furthermore, because the AVK Series 36 is a single integrated unit, it requires less effort to install and is not as physically demanding on the installation team as an equivalent flanged gate valve.

In a timed trial at McCrae Training a flanged gate valve and an AVK Series 36 gate valve were installed in the same trench. The results speak for themselves. For full details of the trial, download our report on the link below.

50% Improvement in Productivity

Let’s do some basic math to identify how many valve installations can be completed by a team of engineers in a day.

  • The AVK Series 36 PE-Tailed Gate Valve takes only 57 minutes to install.
  • It takes 95 minutes to install an equivalent flanged gate valve.

An installation team of two engineers has 450 minutes (7.5 hours) of productive time in a working day. It is given that there is an average 15 minute interval between each installation to move to the next location and set up. A team could install 6 AVK  Series 36 PE-Tailed Gate Valves in a working day compared to 4 equivalent flanged gate valves. That’s a potential productivity gain of 50%.

Imagine how this improvement would impact on your productivity over a week, a year, or AMP8.

AVK Smart Water helps protect and secure your assets

AVK Smart Water can locate issues, detect failures and report on potential leakage in almost real-time. This ensures an incident can be addressed before it becomes critical. AVK Smart Water can also provide insightful data to help optimise overall network performance.

Furthermore, implement joined-up thinking across your divisions, your company and the broader water network by sharing AVK Smart Water data and use the insights to benefit the construction of future networks.

Our website uses cookies for statistical analysis, to improve our website and serve you optimally. By browsing our website or closing this banner, you consent to the use of cookies.
Cookie Policy